In industrial production, many sites require the use of metal tube float flow meters. So, how to install metal tube float flow meters correctly and what wiring precautions need to be taken? Let's introduce them in detail below
1Metal rotor flowmeterThe instruction manual specifically requires the flow to be installed on the pipeline.
2. The head of the explosion-proof metal rotor flowmeter must be powered off before the case can be opened.
3. Open the cover of the remote signal box, and after wiring according to the diagram, be sure to tighten the fastening screws of the cover or hood to prevent dust and dripping.
4Metal rotor flowmeterAfter the cable passes through the introduction device, tighten the compression nut to fix the cable. If the compression nut is not needed, it can be made on the cable conduit with a thread of M18 × 1.5 and directly screwed into the cable introduction device seat.
6Metal rotor flowmeterIt should be installed vertically on a vibration free pipeline without obvious inclination, generally not exceeding 5 ℃, otherwise it will bring unnecessary measurement errors.
7. The control valve of the metal rotor flowmeter must be installed at the outlet of the flowmeter to fill the pipeline section for measuring the flow rate with the medium.
8. The inlet end of the flowmeter should have a 10DN straight pipe section, and the outlet end should have a 5DN or>250mm straight pipe section. DN is the nominal diameter.
9. If the measured medium contains magnetic particles, a magnetic filter should be installed to ensure the normal use of the metal rotor flowmeter.
10. To facilitate disassembly, a bypass pipeline should generally be installed.
11. Flow meters with remote transmission should not have input wires arranged parallel to other power lines, and shielding should be considered to prevent interference from external magnetic fieldsMetal rotor flowmeterTraffic work.
12. Intrinsic safety explosion-proof typeMetal rotor flowmeterSafety barriers such as LB803S must be installed and wired strictly according to the wiring diagram. For detailed installation instructions on safety barriers, please refer to the user manual provided by the product manufacturer.
13. IfMetal rotor flowmeterThe unstable pointer jumping is caused by the unstable flow rate. A flowmeter with damping provided by the manufacturer can be selected. At the same time, the possibility of two-phase flow in the medium (i.e. the presence of liquid and gas phases simultaneously) should also be considered. It is the main factor causing float jumping. To avoid severe impact of the float, the bypass valve should be opened first when opening the flowmeter, and then the inlet and outlet valves should be opened. When there is no bypass valve, the instrument inlet valve should be opened first, and then the instrument outlet valve should be slowly opened, especiallyMetal rotor flowmeterWhen used for gas measurement, due to the low pressure at the outlet of the instrument, the inlet valve of the instrument must be fully opened and the flow rate must be adjusted by the outlet valve of the instrument.